The Tinau Run-of-River Hydropower Project is a 25 MW peaking facility developed on the Tinau River in Palpa District, supplying clean power to the Integrated Nepal Power System (INPS). National Tech Hydro & Electric served as the engineering, procurement, and commissioning partner across all civil, mechanical, and electrical scopes.
From initial feasibility through hydraulic modeling, headworks design, penstock fabrication, and turbine-generator installation, our team coordinated more than 35 specialists and 14 vendor partners to deliver the project on schedule and within budget.
The project required careful hydraulic and geotechnical analysis to balance environmental flow obligations with peak-hour generation. Our team performed CFD-based intake modeling, conducted three rounds of geotechnical surveys, and worked closely with the Department of Electricity Development to secure all required approvals well in advance of construction milestones.
All electrical works — switchyard, transformers, protection relays, control systems, and grid synchronization — were executed in-house under NEA's interconnection standards, ensuring seamless commissioning and first synchronization on the planned date.
Visual documentation of key construction, electromechanical, and commissioning milestones.
Six integrated work packages delivered across civil, mechanical, electrical, and operational domains.
Hydrological assessment, geotechnical investigation, CFD modeling, and detailed engineering drawings stamped by certified professional engineers.
Diversion weir, intake, settling basin, 3.2 km headrace tunnel, surge shaft, and powerhouse civil works to IS-3370 specifications.
Pelton turbine installation, runner balancing, governor commissioning, and complete mechanical balance-of-plant integration.
Generator installation, 132 kV switchyard, transformers, protection relays, and SCADA-based grid synchronization with NEA.
Wet commissioning, performance tests, load rejection trials, and protection scheme validation per IEC 61400 and NEA Grid Code.
Operator training, complete as-built documentation, spare parts kits, and a 24-month operations & maintenance support contract.
36 months from groundbreaking to grid synchronization — delivered ahead of schedule.
Full feasibility report and PPA framework approved by the Department of Electricity Development and Nepal Electricity Authority.
Site mobilization, access road construction, and start of headworks excavation under monsoon-aware scheduling.
3.2 km headrace tunnel completed with full geological documentation and grouting program.
Two Pelton turbines, generators, and governor systems installed and individually pre-tested.
132 kV switchyard energized, protection scheme verified, and station auxiliary systems brought online.
Successful first synchronization with INPS, performance testing complete, and final handover to operator.